CryptoUniverse operates data center in Kirishi.

It was launched in August 2018. Its power is about 20 MW and this is one of the most powerful data centers in Russia. Construction took about a year and gained more than $10 million of investments.

CU Data Center LLC operates data center in the Republic of Karelia.

The first phase of data center in Nadvoitsy was launched in November 2019. This data center is located on 10000 square meters at the territory of RUSAL factory. More than 120 MW power and 54000 are estimated to operate by 2022. 3 buildings of the whole construction with more than 6000 installed miners are done by June 2020. We are currently constructing the first phase of the fourth building to place 15000 miners and planning the second phase of the fourth building to place 15000 more miners.

 

K0 5 MW
Miners (active/capacity) – 3200/3200
Specialization – BTC
Status – ready

 

K1 5 MW
Miners (active/capacity) – 1400/3200
Specialization – BTC
Status – installing additional equipment

 

K3 2,5 MW
Miners (active/capacity) – 1300/1300
Specialization – BTC
Status – ready

 

K2 26 MW
The first phase – Q3 2020
Miners (active/capacity) – 0/15000
Specialization – BTC
Status – being constructed

K2 26 MW
The second phase – Q4 2020
Miners (active/capacity) – 0/15000
Specialization- BTC
Status – planning